Oliver Bridge Rail Road Deck Project Hopes to Be Completed by November 17th

Photo courtesy of Jeanne Ryan/TSM
Photo courtesy of Jeanne Ryan/TSM

The CN Oliver Bridge rail deck has 72% of the rail deck replaced with the remaining materials on site and ready to be installed during non traffic hours.

These daytime closures of the roadway are beneath the rail bridge connecting Wisconsin Hwy 105 to Minnesota Hwy 39. The Wisconsin portion of the project was completed this past August.

The benefits of this project are to improve the safety and extended life of the bridge. And, Improve the safety and efficiency of railroad networks. For more information on this project Click Here

Latest From Mix 108

Recommended for You

Best of the Web

Leave a Comment

It appears that you already have an account created within our VIP network of sites on . To keep your personal information safe, we need to verify that it's really you. To activate your account, please confirm your password. When you have confirmed your password, you will be able to log in through Facebook on both sites.

Forgot your password?

*Please note that your prizes and activities will not be shared between programs within our VIP network.

It appears that you already have an account on this site associated with . To connect your existing account just click on the account activation button below. You will maintain your existing VIP profile. After you do this, you will be able to always log in to http://mix108.com using your original account information.

*Please note that your prizes and activities will not be shared between programs within our VIP network.

Please fill out the information below to help us provide you a better experience.

(Forgot your password?)

Not a member? Sign up here

Sign up for MIX 108 All Access quickly by connecting your Facebook account. It's just as secure and no password to remember!

Sign up to have exclusive MIX 108 All Access contests, events, coupons, presales, and much more delivered to you for FREE.